Single-Storey Extension: The Stages in Order
Most extension stress comes from decisions being asked for later than expected. The build follows a fixed order, and each stage closes off choices behind it. Here is the sequence and the point at which each decision genuinely has to be made.
Before anything is dug
Drawings, structural calculations, building control application, and where the work is close to a shared boundary, party wall notices with the statutory notice period. Drainage searches matter too — building over or near a public sewer needs agreement with the water authority.
This is also when the kitchen or bathroom layout should be broadly settled, because it dictates drainage positions that get built into the slab.
Foundations and drainage
Excavation, inspection of the trench by building control, concrete, then blockwork up to damp-proof course level. Existing drains are diverted or new runs formed, and any manhole inside the footprint is rebuilt with a sealed cover.
Trees, made ground and shrinkable clay all affect foundation depth, and this is the stage where costs most commonly move beyond the original estimate.
Shell, roof and weathertight
Floor slab and insulation, walls up, lintels and any steel to the opening between old and new, then the roof structure and covering, followed by windows and external doors.
- The knock-through into the existing house usually happens late, to keep the home usable
- Steelwork positions and sizes come from the structural engineer, not the site
- Building control inspects at damp-proof course, before the slab is covered, and at other set points
- Weathertight is the milestone that makes the rest of the programme predictable
First fix, plaster, second fix
Electrics, plumbing and any underfloor heating go in while the walls are open, then insulation and boarding, then plastering. After drying, second-fix joinery, sanitaryware, sockets and switches, flooring and decoration follow in that order.
Kitchen and bathroom specifications must be confirmed well before first fix, because pipe and cable positions are set then.
Completion
Final building control inspection and completion certificate, electrical certification, any gas safety documentation, and a snagging walk-round. Keep all of it — a buyer's solicitor will ask for the completion certificate.
Want a professional to handle it?
Request your free, no-obligation quote through our enquiry form — it takes under two minutes and goes straight to Elliot.
Request my free quoteYou'll be taken to our secure TradeHQ enquiry form. We reply within 48 hours. Prefer to talk? Call 07850 357962.
Frequently asked questions
Talk it through before you spend anything
Send your drawings, or a sketch and photos, and we will set out the stage-by-stage programme for your build.
Related services
Covering Kent, East Sussex & Surrey.
Related pages
More guides
Costs, Process & Regulations
What actually drives the cost of rendering a houseCosts, Process & Regulations
Replastering a room: what actually happensCosts, Process & Regulations
How long plaster needs before paintingCosts, Process & Regulations
The garden room build process, stage by stage