What Should an Extension Quote Include?
Most people compare quotes by looking at the total, which is the one figure that tells you least. A quote is a description of work with a price attached, and if two descriptions differ, the prices were never comparable. Here is what a quote should actually contain.
The scope, in enough detail to argue with
A quote should describe the work stage by stage, not in a single paragraph. Groundworks and foundations, drainage, structure and steels, roof, windows and doors, first fix, plastering, second fix, decoration, external works and making good.
If you cannot tell from the document what will and will not be done, you cannot hold anyone to it later, and neither can they defend themselves.
The line items to look for
These are the ones most often absent, and each one is capable of moving the total noticeably.
- Scaffold, including how long it is allowed for
- Skips and muck away, and who pays if the ground yields more spoil
- Building control charges, and whether the builder or you pays them
- Structural steel supply, fabrication and installation
- Making good to existing rooms opened into
- Decoration, and whether it is included or excluded
- Kitchens, appliances, sanitaryware and flooring, priced or excluded
- Welfare, site protection and cleaning
Provisional sums and what they mean
A provisional sum is an allowance for work that cannot yet be priced accurately, most often foundations before the ground is open. It is a legitimate and honest device, not a trick, but it is not a fixed price for that item.
What matters is that provisional sums are clearly identified, few in number, and that the quote says how the final figure will be established. A quote that is mostly provisional sums is an estimate dressed as a quote.
Payment terms
Expect payments tied to completed stages rather than to dates, with the amount reflecting work actually done. A modest deposit for materials procurement is normal. A large payment before anything happens is not.
There should also be a retention or a final payment held until snagging is complete and any certificates have been handed over.
Programme, insurance and the paperwork at the end
A quote should carry a programme with stage dates, confirmation of public liability insurance, and a statement of what will be handed over on completion: building control completion certificate, electrical certification, gas safety documentation where relevant, and any guarantees.
That closing paperwork is what a buyer's solicitor asks for years later, and its absence is a genuine problem at the point of sale.
Warning signs
A single line total with no breakdown. Pressure to decide quickly. A large upfront payment. No written programme. Reluctance to provide insurance details. A price conspicuously below the others, which usually means something has been left out rather than that a bargain has been found.
Want a professional to handle it?
Request your free, no-obligation quote through our enquiry form — it takes under two minutes and goes straight to Elliot.
Request my free quoteYou'll be taken to our secure TradeHQ enquiry form. We reply within 48 hours. Prefer to talk? Call 07850 357962.
Frequently asked questions
Talk it through before you spend anything
Our quotes are issued itemised by stage with exclusions listed explicitly, so you can compare them properly against anyone else's.
Related services
Covering Kent, East Sussex & Surrey.
Related pages
More guides
Costs & Budgeting
Single storey extension cost guideCosts & Budgeting
House extension cost guideCosts & Budgeting
Loft conversion pricesCosts & Budgeting
What drives loft conversion cost