Order of Works for a Full House Renovation
Nearly every expensive renovation mistake is a sequencing mistake: a beautiful new floor laid before the plastering, a kitchen fitted before the rewire, decoration completed before the roof leak was found. Work outside in, top down, rough to fine.
1. Make it watertight and structurally sound
Roof, gutters, external walls, windows and any structural repairs come first. Everything downstream depends on the building being dry, and a leak found after plastering means paying twice.
Structural work — beams, wall removals, chimney breasts, new openings — also belongs here, because it creates the most disruption and dust.
2. Strip out and resolve damp
Remove what is going, expose what needs inspecting, and deal with damp at its source. Allow drying time in the programme rather than discovering it as a delay later.
3. First fix
With walls and floors open, all the buried services go in at once.
- Rewire, including every socket, switch and light position agreed in advance
- Plumbing and heating pipework, radiator positions, underfloor heating
- Waste and soil runs for new bathrooms and kitchens
- Data, TV, alarm and any speaker cabling
- Insulation, then studwork, boarding and window boards
4. Plaster, then dry out
Plastering happens once, over the whole house where possible, and then the building needs ventilating. This is the stage people compress and it is the one that punishes them, because everything decorative sits on top of it.
5. Second fix and finishes
Joinery, doors, skirting and architrave, sanitaryware, kitchen, sockets and switches, then decoration, and flooring last or second-to-last depending on the material.
Floor finishes go in as late as practical to avoid damage, with the exception of tiling that needs to run under fitted units.
6. Snagging and documentation
A walk-round in good light with a list, then certificates gathered in one place: electrical installation certificate, gas safety, building control completion, any guarantees on roofing, render or damp work. This is the paperwork a buyer's solicitor will ask for years later.
Want a professional to handle it?
Request your free, no-obligation quote through our enquiry form — it takes under two minutes and goes straight to Elliot.
Request my free quoteYou'll be taken to our secure TradeHQ enquiry form. We reply within 48 hours. Prefer to talk? Call 07850 357962.
Frequently asked questions
Talk it through before you spend anything
Send photos and a rough scope and we will set out the sequence and where the decision deadlines fall.
Related services
Covering Kent, East Sussex & Surrey.
Related pages
More guides
Costs, Process & Regulations
What actually drives the cost of rendering a houseCosts, Process & Regulations
Replastering a room: what actually happensCosts, Process & Regulations
How long plaster needs before paintingCosts, Process & Regulations
The garden room build process, stage by stage